News for hackers. Stuff that matters.
Re:Sheep grazing in solar fields offers farmers economic, ec... by Onavo on Monday November 16, 2026 @01:01PM (#50520650)
I have a question, how are they burying the power cables? Are they above ground or underneath?
Re:Sheep grazing in solar fields offers farmers economic, ec... by SoftTalker on Monday November 16, 2026 @01:07PM (#50520727)
Likely underground I'd think. Voltage off of the panels is relatively low, so buried cables should be fine.
Re:Sheep grazing in solar fields offers farmers economic, ec... by quickthrowman on Monday November 16, 2026 @01:10PM (#50520767)
Direct burial PV cable (600V or 2kV rated) or in Sch 40/Sch 80 PVC conduit.

Direct burial PV cable https://www.wireandcableyourway.com/solar-photovoltaic-pv-wi...

Re:Sheep grazing in solar fields offers farmers economic, ec... by KaiserPro on Monday November 16, 2026 @01:18PM (#50520876)
All the cables need to be managed. mainly because you can't keep all the bastard animals out.

Solar panels are joined together into "strings" which means that you have something like 12-18 panels in series. Those strings are joined into a combinerbox that takes 8-15 strings and join them into one big lump.

Each string is >500volts DC. So they need to be protected from both sun and animals.

The main animal oopsey is where the strings enter the string combiner box. the stings come straight out the back of the panels, run along the mounts and then into the combiner at the end of the row. When the strings emerge into the combiner box, they are protected by a metal cage.

The big fat combined cable then goes into a ground conduit to go to the inverter.

Re:Sheep grazing in solar fields offers farmers economic, ec... by scblock on Monday November 16, 2026 @02:29PM (#50521882)
Most utility scale multi-megawatt solar is designed for 1500 VDC, so depending on weather conditions string voltage will be in the 900-1200 VDC range, typically. Those will have string lengths in the mid-20s instead. The exception is thin film modules from First Solar, which have higher per-module voltage and will probably have 6 strings instead.

In my experience the cables will probably run straight into the combiner box, and then into the ground without additional protection, then over to the nearest inverter and transformer.

I have also seen a few projects with the cables run above ground on hangars, though this is less common.