News for hackers. Stuff that matters.
Re:Greenvolt begins building 600 MW/2.4 GWh BESS in Poland by thechao on Monday October 05, 2026 @04:30PM (#49970256)
I don't know about other states, but Texas has about 18GW of BESS, already (https://www.cleanview.co/power-projects/operating/battery-st...). We're planning another ~177GW (https://www.ercot.com/files/docs/2026/04/16/ERCOT-Monthly-Op...).
Re:Greenvolt begins building 600 MW/2.4 GWh BESS in Poland by pampas on Monday October 05, 2026 @06:50PM (#49971883)
Surely capacity should be GW hours?
Re:Greenvolt begins building 600 MW/2.4 GWh BESS in Poland by thechao on Monday October 05, 2026 @07:53PM (#49972358)
I dunno. I vacillated on that. It's something like 45–50 GWh nameplate currently installed, and ERCOT has 177 GW / 371 GWh of active planned battery projects in the interconnection queue. BESS are used for peaker-like capacity and load balancing, so GW is actually a pretty relevant number here.