The bottleneck is the grid, not the production centers. Volatility is not more extreme in Sweden than other connected (Nord Pool) countries. Companies lament the lack of grid connectivity all the time. Then they get the offer "Pay for the cost of grid expansion to connect you" and they are not so interested anymore.