And there's no reason we couldn't have used other reactor designs, apart from lack of financing so only EDF gambled everything on the EPR for HPC (again) and failed to deliver on time/on budget (again).
>Hinkley Point C has a contracted price of £133/MWh. I imagine there's some risk-sharing and inflation in the contract so this will probably go up. Compare this to £65/MWh for new solar and £72/MWh for new onshore wind [3]. Plus of course that wind and solar projects don't take 20 years to come online.
In 2012 prices HPC was £89/MWh. AR7 is delivering (in 2012 prices) offshore wind for ~£65/MWh.
But regardless these aren't comparable at all, for the reasons I set out above. That £65/MWh often doesn't include grid upgrades (which aren't required to nearly the same scale for nuclear, as they tend to be nearish existing population/demand centres and have existing grid infra). AND you still need (expensive) backup for that wind. We are building (right now!) new gas peaking plants that are allowed by law to only operate 10 days per year. The cost per MWh if you include that capex is horrendous.
>Lastly, the only way the per MWh costs can even get that low is by giving Hinkley Point C a 60 year lifespan to amortize the cost over a sufficiently large timespan. It's likely that as the plant ages, operational costs will significantly increase beyond what's projected.
Not true, HPCs 'agreement' is for 35 years. After that they just get the market price, so it is not based on the 60 year lifespan per se.
> Not true, HPCs 'agreement' is for 35 years. After that they just get the market price, so it is not based on the 60 year lifespan per se.
So this gives away my point. The plant has a lifespan of 60 years and a rate agreement for 35 years. Why the discrepancy? Because it's going to get an awful lot more expensive in 35 years and the government (within limits) will have to pay it.
So basically we've given HPC a lifespan of 60 years to reduce the costs and only negotiated 35 years to pretend maintenance isn't going to significantly increase that cost.
Obviously there is some investment needed but if you take a look at the capex cost of the north Scottish grid upgrades PLUS the HVDCs it's pretty terrifying.
The idea is that the financing will be "paid off" after 35 years so it doesn't require a "guaranteed" price after that (it reduces finance costs significantly when HMG is underwriting the main payback period. I expect the remaining 25 years will be extraordinarily profitable for EDF. Even if there is more maintenance costs they will have no finance costs. And finance is the main cost of HPC (60-70% goes to interest payments on the debt).
Planning began for Hinkley Point C in 20113. It was approved in 2016. Construction commenced in 2017-2018. It's hit major delays and is currently projected to come online in 2030. It could be delayed furhter. Unit 2 is expected about a year later [1]. Cost have ballooned to almost £50 billion [2] and may balloon further.
So you're looking at almost 20 years to build, £50 billion in costs and electricity production of ~3.2GW.
AFAICT that 3.2GW is ~7% of the UK's current electricity requirements so I'm not sure where you're getting "nearly all electricity demand". Also, 5 Hinkley Point Cs would be 16GW of electricity not 30GW.
Hinkley Point C has a contracted price of £133/MWh. I imagine there's some risk-sharing and inflation in the contract so this will probably go up. Compare this to £65/MWh for new solar and £72/MWh for new onshore wind [3]. Plus of course that wind and solar projects don't take 20 years to come online.
Lastly, the only way the per MWh costs can even get that low is by giving Hinkley Point C a 60 year lifespan to amortize the cost over a sufficiently large timespan. It's likely that as the plant ages, operational costs will significantly increase beyond what's projected.
[1]: https://eandt.theiet.org/2026/02/23/hinkley-point-c-faces-fu...
[2]: https://www.telegraph.co.uk/business/2026/02/20/hinkley-poin...
[3]: https://www.carbonbrief.org/qa-new-uk-onshore-wind-and-solar...