Re:Court orders restart of all US offshore wind power constr...
by bob1029 on Tuesday February 03, 2026 @04:43AM
(#46868797)
> Gas generators can be spun up to provide megawatts in seconds btw
Only if they're already spinning and everything is hot and ready.
Non-spinning reserves can take hours to bring online. Cold power plants cannot be brought up quickly. The simplest designs can ramp within a few minutes, but these are generally not intended for any kind of continuous operation due to efficiency concerns.
Gas generators can be spun up to provide megawatts in seconds btw. With less than a quarter of the grid being renewable, intermittency is not an issue. Grids are built with resilience in mind (or at least should be...).