Re:How much revenue is needed to justify the current AI spend?
by martinald on Sunday October 12, 2025 @08:53AM
(#45557900)
It's been worse than that. Datacentres are needing basically completely rebuilt for especially Blackwell chips as they mostly require liquid cooling, not air cooling as before. So you don't need to just replace the hardware, you need to replace all the power AND provide liquid cooling, which means completely redesigning the entire datacentres.
With GPUs and CPUs. You need to replace entire thing. And now they are the most expensive part of the system.
Other option is doing more with same computing power, but we have utterly failed with that in general...