Re:Italy moves to reverse anti-nuclear stance by pfdietz on Wednesday March 05, 2025 @03:48PM (#43272162)
Here's the report:

https://www.ccomptes.fr/sites/default/files/2025-01/20250114...

What they said about EPR2 is that they were refused the information to even make an estimate of its profitability. Translation (using DocLingo) from page 25:

"In its 2020 report on the EPR sector, the Court recommended that EDF 'calculate the projected profitability of the Flamanville 3 reactor and the EPR2 and ensure its monitoring' (recommendation no. 6). EDF has deliberately and persistently refused to provide the Court with information on the projected profitability and production costs, which leads to considering this recommendation as not implemented. work.

Based on the information at its disposal, the Court's calculation predicts a poor profitability for Flamanville 3. For its part, the EPR2 program is still characterized by the absence of a finalized estimate and a financing plan."

Any claims of profitability of EPR/EPR2 should be taken with heavy skepticism, given that the official auditors have been stonewalled.