The cost to build a loop of transmission across the entire US is EXTREMELY expensive. It costs billions just for short segments of transmission.
[ Parent
| on HN ]
The only reason to build them is because they lower your total costs. Over its lifespan the value of power lost in transmission over a 1,000km HVDC line in regular operation is significantly more than the direct costs to build and operate one. But you can get a lot more efficiency building solar in Nevada vs the northeastern US which more than pays for those costs.
So, if by short distances you’re talking 1,000+km and 10GW then sure it’s billions. However, the US is only so big and Billion’s don’t actually mean much to move over 2% of the US’s total electricity.