News for hackers. Stuff that matters.
Re:Cement recycling method could help solve one of the big c... by s1artibartfast on Thursday May 23, 2024 @05:58PM (#40460392)
Do they operate 24/7?

Even if it is batch process, going from 24 hours to 8 hours is like tripling plant cost vs productivity.

Re:Cement recycling method could help solve one of the big c... by kragen on Thursday May 23, 2024 @08:08PM (#40461436)
tripling capex vs. productivity, yes, but maybe if capex is small compared to opex, that's a worthwhile tradeoff. the one particular plant i was able to find the answer for does operate 24/7
Re:Cement recycling method could help solve one of the big c... by adgjlsfhk1 on Friday May 24, 2024 @01:00AM (#40462939)
don't forget wind. there's lots of wind power and very low power consumption at night. it's probably more like 22 hours to 16
Re:Cement recycling method could help solve one of the big c... by bluGill on Friday May 24, 2024 @10:23AM (#40466581)
They generally will run the cheapest electric rates. They commonly run only the overnight shift when electric is cheapest - it is worth paying the employees that extra money to work the overnight shift. They commonly shutdown the entire month of December for yearly maintenance - when Christmas lights add additional electric demand. They coordinate with the power company for other shutdowns.