Re:Zwentendorf Nuclear Power Plant: Finished in 1978 but was... by chickenbig on Saturday May 18, 2024 @03:09AM (#40397033)
It is a good job the station's Finnish owner/operator, TVO, got it on a fixed price contract. That does not make coping with the delays in coming online any easier, but some consolation that someone else is footing the construction bill and enriching the local economy.

This is, to some extent, the same as Hinkley Point C where EDF and CGN have got a long term strike price. I wait with interest to see how Sizewell C will be financed, be it the regulated asset base model or else a Contract For Difference.

There is a good argument for cost-plus construction contracts provided the purchaser can financially cope with the risks. Risk transfer is never free!

Re:Zwentendorf Nuclear Power Plant: Finished in 1978 but was... by moogly on Saturday May 18, 2024 @06:00AM (#40397710)
> someone else

Indeed. That would be French taxpayers.

Re:Zwentendorf Nuclear Power Plant: Finished in 1978 but was... by chickenbig on Sunday May 19, 2024 @10:55AM (#40407353)
EDF has only recently become fully state owned. Also the French state have recently amended the ARENH arrangement to get greater revenues (who knew selling options for 42 EUR/MWh was a bad idea). Greater losses and damages have been incurred by previous governments.

https://www.world-nuclear-news.org/Articles/Agreement-on-pos...