Re:There's Not Enough Power for America's High-Tech Ambitions
by StevenHarlow on Sunday May 12, 2024 @11:14AM
(#40335133)
Not all of that capacity in the interconnection queues are ready to flip the switch though, correct? Requests can be pre-construction, construction, built/non-operating, and operating [1]
[1] https://www.enverus.com/blog/the-interconnection-queue-an-in...
Unfortunately it takes 10 years to build new transmission lines in the US [3]. Changes are going to need to be made to the process, which may include giving more responsibility and agency to FERC to oversee the review process.
[1] https://emp.lbl.gov/utility-scale-solar
[2] https://www.eia.gov/energyexplained/electricity/electricity-...
[3] https://yaleclimateconnections.org/2022/10/permitting-americ...