Re:The Time I Lied to the CTO and Saved the Day
by Fin_Code on Thursday May 09, 2024 @11:00AM
(#40308922)
If they said they were done then the next work would be demanded with holidays cancelled. By padding they got time off.
Re:The Time I Lied to the CTO and Saved the Day
by unnouinceput on Thursday May 09, 2024 @10:56AM
(#40308887)
CTO had personal connections with the vendor. I suspect personal means the wife or sister was there and they had this as a family business. You know "here is money from my company that go to your company and each of us will get a big pie off it" type of shady deal.
Re:The Time I Lied to the CTO and Saved the Day
by CRConrad on Saturday May 11, 2024 @07:50PM
(#40331366)
As I understood it, they weren't quite done. They were at, say, 90%, and confident they could do the last 10% after holidays and before release.
But the CTO insisted on Death March-style hours, so the author told the CTO they were at 80%, and then doled out the milestones from 80% to 90% over the week his team was away.
Had he said "Uhh, hey boss, we're already at 90%", the CTO would have said "Great, then work 26/8 over Christmas to get to 100%!".
Or did I misread something?