Re:All I want for Christmas is 1TW of solar deployed annually by cinntaile on Tuesday December 26, 2023 @06:23AM (#38770805)
You can (and this is being done in practice) regulate the power output instead of turning it off completely and then turning it on again, doing it your way would be extremely detrimental to the power plant's life due to thermal stress. It's also the case that different coal plants have different capabilities so when you claim it takes a around week to turn off a plant, you should provide some more information about the plant (type) you're talking about.
Re:All I want for Christmas is 1TW of solar deployed annually by TheLoafOfBread on Tuesday December 26, 2023 @07:05AM (#38771081)
You can disconnect output, yet you need to still burn coal anyway, unless you want to damage the coal power plant.
Re:All I want for Christmas is 1TW of solar deployed annually by cinntaile on Tuesday December 26, 2023 @07:54AM (#38771360)
I'm not talking about disconnecting output, I'm talking about reducing it. You don't burn as much coal, which was my original statement.
Re:All I want for Christmas is 1TW of solar deployed annually by TheLoafOfBread on Tuesday December 26, 2023 @09:08AM (#38771851)
But idle = power plant still running on 80% so you are still using 80% of coal input to just keep it running on empty.
Re:All I want for Christmas is 1TW of solar deployed annually by cinntaile on Tuesday December 26, 2023 @09:40AM (#38772128)
Coal plants for load following end up around 20-40%, nowhere near your 80% number. They have to, because the energy grid demands that they're capable of doing this because it's just not economical to run them at 80% when there is such variability.