Re:How the data center site selection process works at Dropbox
by ramraj07 on Friday June 30, 2023 @11:31PM
(#36546182)
Our Indian Condo complex generator regularly takes more than 30 seconds to start up. Even the best case is likely at 10 seconds so only having such a small cushion sounds dangerous.
Re:How the data center site selection process works at Dropbox
by rainbowzootsuit on Saturday July 01, 2023 @12:20AM
(#36546539)
Some rough calculations on a fully loaded data center that I have worked on designing shows that you only have about a minute before the air gets to an overheating condition due to the low heat capacity. The HVAC doesn't keep running through a total power failure even if the computers have a lot of reserve power.
If a generator fails to start in 30 seconds, that almost always means it will also not start within 5 minutes.
Does dropbox have automation that attempts to gracefully shut down systems if a generator fails to start? Are systems then kept down until the battery UPS system is fully recharged? If not, the difference between 30 seconds and 5 minutes doesn’t seem important.