Re:Rules of Thumb for Software Development Estimations by ohthehugemanate on Wednesday May 03, 2023 @10:18AM (#35802688)
It's not rocket science, but I can't speak for how your teams have been doing it. I know there's a tremendous number of well meaning people who get certified in a rote method and only understand it as dogma. Doing this right only requires understanding the underlying principles and figuring out a method that your team likes.

Principles are:

- humans are much better at estimating relative effort than average time. So estimation sessions are only in terms of effort. The answer to "how many hours is one point?" is "as long as it takes." With developers like you this can be a hard line to keep but it is absolutely full stop required.

- consistency in relative effort unit sizes is a requirement for the math to work. Group estimation does this automatically after a few sessions, and can help expose miscommunications and better architectures along the way... but it's not the only way to do it.

- a consistent yardstick for "done" is required for consistent unit sizes. (Logically)

- project managers track average number of points completed per sprint. Even though this average will become extremely consistent, it is an AVERAGE ONLY and can not predict any individual sprint.

- There is no pressure to burn points "faster". Remember, point sizes are arbitrary and consistency is required. When engineers feel pressure to complete more in the same time, consistency is dropped and the math breaks) if you are using sprints this is an easy trap to fall into. More points per sprint != better. Making tasks easier is OK though, ie with automation or technical improvements. Note that this would impact the estimated point size of your tasks, not the number of points put through in a sprint!

That's it. Do it how you want, but have consistent relative point sizes, don't let engineers talk or think about time, don't treat an average like a single sprint prediction, and don't pressure engineers to increase velocity.

A casino can't predict a single hand, but they can predict with great accuracy their profit margin after 100 hands. Using the same math, you can't predict a single sprint, but you can predict with great accuracy 5, 10, or 20 sprints... as long as you help the developers stay unpressured and therefore consistent.

ALL THAT SAID, when you say "I did this before, it took me 2 weeks," that is also a very effective way to estimate. If your tasks are highly consistent, definitely track time for implementation of similar work (because human memory is very fallable) and estimate this way. Just don't let yourself notice that you defined a consistent unit of effort and used past average time to predict future average time, and you can feel like you've found a great life hack.

Re:Rules of Thumb for Software Development Estimations by dragonwriter on Wednesday May 03, 2023 @10:30AM (#35802846)
> The answer to "how many hours is one point?" is "as long as it takes."

In principle the “how many hours to one point” question is answered by tracking and analysis of past sprints, where over time you develop an empirical measure of velocity, which gives you an idea both of the average time it takes to do a atory of a particular size, but also the size of the error bars when taking that average as an estimate.

Which can be useful for sanity checking things like sprint sizing, though the existence of the stat risks it becoming an optimization target in some orgs, either because management sees it and wants “line goes up” or for some other reasons (teams can do it to themselves, though management is more likely to.)

Re:Rules of Thumb for Software Development Estimations by sanitycheck on Wednesday May 03, 2023 @12:36PM (#35804444)
Well no, and rocket science works which is one difference.

I've been through all this with multiple teams/companies and I wasn't always even opposed to the idea! In the end all point-based estimates seem to do is add more ways to be wrong.

Humans are actually pretty good at estimating absolute time if they've had some practice. After the first few times you estimate a day and it takes a week, you realise you're an optimist and you should compensate for that. It seems the wrong conclusion to draw would be "oh well it's impossible, I should use made-up units instead", just get better at it. There was a time I was mostly doing fixed-price work, nobody would have accepted points in a quote and nobody would pay me per point.

Consistency in unit sizes is basically impossible, from what I've seen - unless there's an unspoken but commonly understood translation to units of time.

Project managers who try to size sprints in points tend to eventually give up, after finding that the the actual effort taken varies so wildly between sprints. (I also tend to think sprints suck, and Kanban is the way to go for agile - but that's another topic.)

Re:Rules of Thumb for Software Development Estimations by chasd00 on Wednesday May 03, 2023 @02:43PM (#35806103)
> There was a time I was mostly doing fixed-price work, nobody would have accepted points in a quote and nobody would pay me per point.

I've done that too and fixed-price work is like handling dynamite. I've always felt it was good for new grads to spend a couple years in small, eat-what-you-kill, consulting shops to understand the business of software development better. After that, then go to megacorp/faang or whatever but the lessons learned in a small consultancy will help you see the forest through the trees.

Re:Rules of Thumb for Software Development Estimations by burnished on Wednesday May 03, 2023 @03:33PM (#35806645)
My team does point based estimation and I like it. The points are useful for getting an idea of how much stuff to work on in a sprint and a measure for how much room we need to leave in for the inevitable and consistent problems that we have to pick up mid sprint.

The real benefit imo is that it is a good shorthand during estimation that reveals misunderstandings or flaws in a ticket. Everyone pointing a ticket at a 2 is whatever, literally any time spent discussing if it is a 2 vs a 3 drains my vitality, but every time there is a big outlier or bimodal distribution we get a lot of value from talking it out.

I think what points gets you here over hours is that it focuses on the task at hand. I think a time centric approach requires your estimates to be more like 'X hours for John, Y hours for Shirley'.

I'm not touching your points about how there are other contexts where it doesn't make sense to do this, or the absurdity inherent in pretending that they don't still boil down to time in a meaningful sense because I agree with them.

Re:Rules of Thumb for Software Development Estimations by lumb63 on Wednesday May 03, 2023 @05:17PM (#35807912)
The goal of estimating is to know how long it will take to complete a given task. A successful estimating methodology ought to provide this. I am not convinced the method you outline does provide this.

First, I would be interested to see any data you have supporting the idea that “humans are much better at estimating relative effort than average time”. My own experience is humans have biases toward optimism or pessimism and are poor estimators of the magnitude of risk, but I’ll ignore that for the moment and accept the premise as true.

The other underlying premise of your method is that velocity is a random variable about this perfect prediction with a known distribution, such that via the law of large numbers, over a large number of sprints, the average velocity can be known with high accuracy. I see a few issues with this.

One issue is that velocity is not static. Velocity changes with team morale and how interesting or motivating the task is. It changes with how well engineers are suited to a task. It changes with organizational changes, the addition of new team members, the loss of old ones, the work environment, etc. I don’t buy that these are small factors that average out over the long run, either, since my experience leads me to believe they don’t. A poor work environment or coworkers leaving the team or low morale usually are harbingers of bad things to come, and, opposite, a growing team working usually has exciting challenges, morale is usually high, etc. My experience hasn’t shown a mixed bag of equal good and bad, but instead two divergent sets.

Even if velocity were static, the other issue is the distribution is unknown. Sometimes teams have bad weeks, and sometimes they have good ones. Sometimes something catastrophic happens in the organization and a dozen engineers are twiddling their thumbs or are thrown into some task they did not foresee. Sometimes things go unexpectedly well. A priori, there’s no way of knowing what a particular team tends to, or if that trend will continue. One could try to measure it, but my experience has been that something that was supposed to be static will change long before a sufficient amount of data could be collected to be meaningful.

Even if you knew the exact distribution you’d encounter, the final problem that remains is that projects aren’t infinitely long. There aren’t a million sprints to smooth things out. There will be variation in the outcome.

I guess what I’m saying is, estimates are estimates. Why systematize their creation when they will ultimately be wrong, and creating them is so costly? I could understand having a system if it were low-overhead, but my experience with a system similar to what you’re describing was anything but that.

Re:Rules of Thumb for Software Development Estimations by sopooneo on Thursday May 04, 2023 @12:09AM (#35811078)
I've never been anywhere that used story points effectively, but the notion sincerely appeals to me, and I look forward to being somewhere that has it working.

But there is one practical question that has always confused me: how do you "measure velocity" in Scrum, when each sprint's scope, and the story points within, are all preset at the start of the sprint?

Do we assume (realistically) that dev is not completing all stories within the sprint? Or that they are adding more stories in the middle? Or are we assuming that each sprint is finished exactly as planned, on time, and changes in average "velocity" reflect differing levels of confidence or ambition of the dev team as the decide how many stories to include in each sprint?

In a rough KanBan process, I can see measurement of "velocity" as being more straightforward. Am I missing anything?

Re:Rules of Thumb for Software Development Estimations by ohthehugemanate on Friday May 05, 2023 @08:01AM (#35828155)
Sounds like maybe your experience is with places that do this backwards? Velocity is a backwards looking measure. It doesn't commit your team to grind until that's done.

We get as much done as we get done. We take a guess about how much work that will be at sprint start, based on previous average, and make sure that much work is well understood and prioritized. But tasks turn out to be easier or harder than expected, people get sick, shit happens and you end up accomplishing more or less than what you expected. At sprint end you measure what you actually accomplished, to help predict the long run timeline of the project and maybe to get a better guess at how much work to prep for next time.

There should be no time or "amount done" pressure on the engineers. We measure the actual throughput and use that to inform management how long the work as defined will probably take. If management doesn't like that assessment, they can manage the situation by adding engineers or reducing complexity/scope. If you really like playing with fire you could let them ask to lower quality standards, too.

Re:Rules of Thumb for Software Development Estimations by sopooneo on Friday May 05, 2023 @10:17PM (#35837334)
Got it. That makes sense. And I hear you on how you could accomplish less story points, or tickets, or whatever during a sprint. Happens all the time for the reasons you say.

But how do you accomplish more? Are you in organizations that have enough trust that items can be added to a sprint while it is in process?