Re:Rules of Thumb for Software Development Estimations by switch007 on Wednesday May 03, 2023 @06:14AM (#35800349)
My previous manager and PM would scrutinise the time taken in Jira, then create a personal spreadsheet to roughly map points to hours/days (because senior stakeholders don't think in cups of coffee or t-shirt sizes), then refer to the spreadsheet privately during estimation. But he eventually let slip about the existence of it

So we just bypassed the charade and starting giving hours/days. The whole team was really just doing hours/days -> points mapping in their heads during estimation anyway.

Re:Rules of Thumb for Software Development Estimations by ohthehugemanate on Wednesday May 03, 2023 @10:35AM (#35802909)
> The whole team was really just doing hours/days -> points mapping in their heads during estimation anyway.

This is a common story. But because of the calculation step, your PM was still mapping estimated time units to actual time consumed, and using that mapping for predictions. So you were getting some of the benefits of an abstracted unit (accuracy, averaging in unexpected events) without the stress reduction or focus on quality over time.

But if it worked for your team, I would advocate to keep it. Human groups are hard enough to coordinate as it is, there's no need to hew to a dogma.