Re:Why Construction Projects Always Go over Budget
by maratc on Wednesday March 22, 2023 @08:12AM
(#35259861)
You might be overlooking into what I wrote.
One truck can deliver about 8 m3 of concrete. If you need 100 m3, that's about 12 deliveries.
This can be done if 4 trucks make 3 deliveries each, or if 3 trucks make 4 deliveries each. The supplier has several trucks and while each one needs maintenance rarely, the fleet of them needs maintenance almost daily, so the supplier is likely to either over-provision (have a spare truck), or be able to procure one from his competitor across the street. "One of the trucks having an accident" is already planned in on the supplier level.
One truck can deliver about 8 m3 of concrete. If you need 100 m3, that's about 12 deliveries.
This can be done if 4 trucks make 3 deliveries each, or if 3 trucks make 4 deliveries each. The supplier has several trucks and while each one needs maintenance rarely, the fleet of them needs maintenance almost daily, so the supplier is likely to either over-provision (have a spare truck), or be able to procure one from his competitor across the street. "One of the trucks having an accident" is already planned in on the supplier level.