Re:43 Hours on the Amtrak Southwest Chief
by jandrese on Friday February 03, 2023 @10:35PM
(#34651174)
Is it impossible to expand the sidings? Maybe make them 5 miles long? Sure it's not free, but it doesn't seem like it should be outrageously expensive. Is this just classic underinvestment in infrastructure coming back to bite you in the butt?
Re:43 Hours on the Amtrak Southwest Chief
by secabeen on Friday February 03, 2023 @10:47PM
(#34651254)
Not impossible, probably slow. Land must be acquired, base and track laid, switches moved, etc, etc.
Re:43 Hours on the Amtrak Southwest Chief
by jrochkind1 on Saturday February 04, 2023 @10:00AM
(#34654968)
When the cause of the initial delay could be getting bumped by a freight train in the first place... that is particularly frustrating chain of events.
Re:43 Hours on the Amtrak Southwest Chief
by secabeen on Saturday February 04, 2023 @01:01PM
(#34656495)
Yeah, the main issue is mostly that the network is designed for lowest-cost, non-time-sensitive freight, and fast, time-sensitive Amtrak trains inevitably get stuck behind something slow, or waiting for something slow to clear from the other direction. A passenger-first network would look like Japan, with lots of double-track, few sharp turns, etc. It would cost more overall too.
Some additional enforcement might help, but in the end, with most of the network having large single-track sections, and the long trains of PSR, it's just not a network built for timeliness. About 50% of the train load in America is bulk commodities of one form or another (Coal, stone, grain, etc.) All of these commodities are generally stable and non-spoilable. Thus, the customers don't really care much about punctuality. A power plant can maintain some hours or days of inventory in a big pile next to the plant. If the train with the next load of coal is 8 hours late, it has little impact, you just dig a little deeper into the pile before it's refreshed. 8 hours is a big difference to passengers.