I believe a compounding factor in this problem was a 2015 decision to ban onshore wind farms in England.
Leading to the somewhat perverse situation where it's now necessary to build new or bigger lines from Scotland all the way down to the south of England where most of that generated energy is needed.
It turns out the lead time to build long power lines is long and it is a politically difficult proposition because you have to get permits for a whole line from Point A to Point B.
One of the ways where the sticker price of renewables is higher than what is quoted is the cost of transporting it and one advantage of nuclear is it could be sited closer to demand in some cases.