Hinkley Point C: In 2012, the “strike price” – was set at £92.50 per megawatt hour (MWh) + inflation.
Even with comedy level increases in household bills this still looks expensive.
Anywhere in that ballpark though and I think we can talk.
The inflation adjusted strike £92.5 of became £106 in 2021 per wikipedia [2].
Not sure how this strike price arrangement works, but does it follow that the UK government did not need to subsidize Hinkley Point C in 2021, and will not have to subsidize it in 2022?
Edit: I did not realize Hinkley Point C is not yet operational. Still, if it were, would it follow that it would make a profit by itself, and would not collect the Government guarantee?
[1] https://www.nimblefins.co.uk/average-cost-electricity-kwh-uk
[2] https://en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_...
It works as an insurance, if you think you can generate electricity for X while making a profit then the government guarantees that you get that amount, taking on the risk that prices might drop or some new tech might undercut your price and guaranteeing a steady cash flow if you deliver electricity.
In return for accepting that risk, they also accept the upside, by taking any extra when the price rises above the strike rate.
Currently there's a few offshore wind farms that are hitting this and returning roughly a billion euros per year.
Am I missing something?
For Hinckly, it's the French taxpayer that will be on the hook if there are cost overruns building the plant, because we already know exactly how much they can make from energy for the next decade. (That's why their CFO resigned when they decided to go ahead: https://www.reuters.com/article/uk-edf-britain-nuclear-idUKK...)
For the UK taxpayer, they'll probably be paying too much for power they could have got cheaper, but at least the price is somewhat limited, unless there's any kind of accident or issues with storage.
The key missing element with nuclear is that you don't have a vibrant market of competitive bidders, which is what drives the price down in wind and solar.
I'll even excuse the lack of clarity of decommissioning the site and long term storage of nuclear waste if you can manage that.