Re:The first Gen III+ Nuclear plant begins fuel loading
by concordDance on Saturday October 15, 2022 @05:26AM
(#33213211)
I'm disappointed that paper contains no cost estimates. Those are the key thing with energy storage.
[ Parent
| on HN ]
Re:The first Gen III+ Nuclear plant begins fuel loading
by leetnewb on Saturday October 15, 2022 @07:09AM
(#33213750)
Here is a framework for government backed research into the topic: https://www.energy.gov/energy-storage-grand-challenge/articl...
Re:The first Gen III+ Nuclear plant begins fuel loading
by pfdietz on Saturday October 15, 2022 @07:52AM
(#33214005)
The paper does contain (rough) cost estimates, specifically the cost per unit of energy storage (about $13/kWh) and the cost per unit of power (from $0.20-0.27/W depending on the choice of gas.) See section V, "Cost".
I'm not impressed with the costing methodology used, but it's probably at least in the ballpark.