News for hackers. Stuff that matters.
Re:The first Gen III+ Nuclear plant begins fuel loading by bullen on Friday October 14, 2022 @03:26PM (#33207795)
I think it's still not pushing anything to the grid, it has just reached crusing power: "Regular production is expected to begin in December 2022."
Re:The first Gen III+ Nuclear plant begins fuel loading by Gwypaas on Friday October 14, 2022 @03:37PM (#33207916)
It is pushing to the grid, but short stints validating different modes of operation. Easier, and more economical, to use the generators than trying to cool another 30% thermal capacity.
Re:The first Gen III+ Nuclear plant begins fuel loading by tuukkah on Friday October 14, 2022 @04:03PM (#33208206)
"The electricity production of Olkiluoto’s third nuclear power plant unit started on Saturday, 12 March 2022, at 12.01 p.m."

"The reactor achieved its design output power 30 September 2022."

Regular production will mean all tests have been completed. They are currently ongoing and yes we can notice it in the electricity price when they test shutdowns and 1600 MW (15% nation-wide) disappears from the supply.

Re:The first Gen III+ Nuclear plant begins fuel loading by bullen on Saturday October 15, 2022 @08:55AM (#33214362)
Where can one see the status of the power plant.

This is VERY concerning as prices where very high as the plant was operating then?

Re:The first Gen III+ Nuclear plant begins fuel loading by tuukkah on Sunday October 16, 2022 @04:00AM (#33221956)
Here's the planned status: https://www.tvo.fi/en/index/production/plantunits/ol3/ol3for...

Here you can see the current and past national totals for nuclear/hydro/wind/solar etc. production. Choose 12 October to see what it looks like when they tested turning the whole 1600 MW off at once: https://www.fingrid.fi/en/electricity-market/power-system/

Many things have affected the prices recently including imports (or lack of) from Sweden and Norway, exports to Estonia, wind and rainfall situation, as well as other nuclear reactors being offline for maintenance.

Re:The first Gen III+ Nuclear plant begins fuel loading by bullen on Monday October 17, 2022 @06:47AM (#33231826)
ok, looking closer at this it seems the production only ramped up in september. Have they explained why radioactive matter was found in the turbine? Impressive that wind produces between 2-3GW!
Re:The first Gen III+ Nuclear plant begins fuel loading by bullen on Tuesday October 18, 2022 @07:29AM (#33245709)
nm, now it's down to 500MW...