Re:Ask HN: How does your company handle late running projects? by roughly on Tuesday September 20, 2022 @11:30PM (#32920545)
Someone I worked with noted there were two types of projects - projects that needed to be done by a date, and projects that needed to be done to a spec. Figuring out which one you're working on is the key - need to release by Christmas? Great, figure out what you can deliver by then and deliver it. Need to meet a compliance target? Great, figure out how long it's going to take.