Re:Delivery Lead Time in Practice
by kqr on Friday August 19, 2022 @02:41PM
(#32524629)
> Not fond of these metrics. Feels easy to gamify and hack. I can just push commit a when it's more mature, good I improved the metric, but reduced tinkering, collaboration with devs and product and probably released a subpar solution.
This is not gamed/hacked -- it's the metric working as designed. It is meant to measure purely how fast you can get commits into production. If you have found a way to do that faster, then the metric should increase to reflect that.
So there are two aspects of the problem: are you delivering fast, and are you delivering something valuable?
The delivery lead time doesn't even pretend to measure whether you're delivering something valuable. You need a different metric for that. And in your example, that would go down by your practise.
This is not gamed/hacked -- it's the metric working as designed. It is meant to measure purely how fast you can get commits into production. If you have found a way to do that faster, then the metric should increase to reflect that.
So there are two aspects of the problem: are you delivering fast, and are you delivering something valuable?
The delivery lead time doesn't even pretend to measure whether you're delivering something valuable. You need a different metric for that. And in your example, that would go down by your practise.