Re:How to drive away your best engineers by ebiester on Sunday July 24, 2022 @08:01AM (#32212596)
Forecasting looks like this: https://medium.com/expedia-group-tech/monte-carlo-forecastin...

It’s running through simulations based on previous team behavior to give a range.

Re:How to drive away your best engineers by biztos on Sunday July 24, 2022 @10:34AM (#32213866)
Don’t you still have to correctly estimate the amount of work (time) to complete each task in your backlog?

You can apply all the “science” you want, but at the bottom of it all you have engineers holding up a card with a “4” on it when the scrum dude says “add date picker to the Foo widget.”

Re:How to drive away your best engineers by ebiester on Sunday July 24, 2022 @11:28AM (#32214392)
When I did this last, we incorporated size of epic instead and looked at number of tickets on average. You still have to break it down but you can take into account the number of added tickets given a large enough sample size.
Re:How to drive away your best engineers by satyrnein on Sunday July 24, 2022 @09:50AM (#32213497)
You still need story point estimates on the previous items, or some reason to believe that previous stories were of similar size (which is also a form of estimate).