A more realistic option for the UK might be a submarine HVDC link to Morocco, sort of a bigger version of Viking Link project, which connects the UK to Denmark. I'd like to know if the technology exists to imort, say, 5% of our electricity via that route.
https://www.statista.com/statistics/322874/electricity-consu...
Annualized, that's an average power of 33.5 GW.
On http://gridwatch.templar.co.uk/ you can see in the yearly demand view that peak demand for the year was under 40 GW.
This initial estimate of 150 km^2 of desert solar farms is too small and your later estimate of 13,000 km^2 is too large. A conservative rule of thumb would be 10 megawatts (real power, annualized) per km^2 of solar farm, which would mean 3,350 km^2 of solar farms for 33,500 average megawatts. Note that solar farm area is larger than solar panel area because solar farms need space between racks of panels.
The linked blog post explains that it doesn't have to be a power line. You could synthesize LNG and ferry that elsewhere (that is, assuming the techniques described do indeed scale, and you don't have salty water trouble, etc. etc. etc)
The sheer scale of this logistical problem dwarfs any other feat attempted.
It really doesn't. I'm a huge fan of back-of-the-envelope maths, and this idea raises some very fun questions. How big would the power line be, if the UK (where I live) was powered entirely by solar panels in the African desert?
The UK's average instantaneous power consumption is around 100GW. Assuming a capacity factor of 5 (which is probably far too low), the power transmission system needs to handle at least 500GW. The current (and somewhat unproven) state of the art in power transmission operates at 1000kv, and can carry 5GW per pylon system. We would need 100 of those operating in parallel. As each of those has a minimum separation corridor of 100 meters, we would need to persuade all of the countries along the route to give us a 4000km x 10km strip of land, as well as the approx. 150sq km of land needed for the panels themselves.
This leads to another fun question - if you want to install 150sq. km of solar panels in the desert and still have enough useful life left in the panels when you're done, how wide does the road need to be to carry all of those, and how many trucks will you need working that several thousand km route?