News for hackers. Stuff that matters.
Re:Texas Bitcoin Miners Power Down as Heat Wave Threatens Gr... by toomuchtodo on Tuesday July 12, 2022 @12:10PM (#32071998)
There is ~100GW of solar generation in ERCOT's interconnect queue.

https://www.rechargenews.com/energy-transition/rampant-solar...

> As of 30 September [2021] developers had 100.3GW of solar capacity in the queue, 42.4GW of utility-scale battery storage, 22.5GW of wind, 13.5GW of natural gas and minor amounts of other technologies such as biomass.