Re:Nuclear turn green as EU parliament approves new taxonomy by kergonath on Thursday July 07, 2022 @11:54AM (#32015627)
> Aren't "modern" nuclear plants such as the EPR all a) very late and b) massively over budget?

The Finnish one was both due to epic project management failures, from bad suppliers with dodgy welds, to changing the reactor design as it was being built to accommodate future regulations. Flamanville is also late and over budget for much of the same reasons (shoddy project management and unreliable suppliers; this time the concrete was out of specs as well). These sort of issues get sorted naturally if yew build in series instead of one-of-a kind.

The Chinese did not have any problem building two, and the British one is progressing more or less as planned.

Also, the EPR is not really a modern design.

Re:Nuclear turn green as EU parliament approves new taxonomy by logifail on Thursday July 07, 2022 @12:15PM (#32015886)
> These sort of issues get sorted naturally if yew build in series instead of one-of-a kind

That would appear to rule out any possibility of rapid increasing nuclear generating capacity if we are going to be forced to build them one after another in order to work out how to do it well?

> The Chinese did not have any problem building two

...that they've admitted to?

> the British one is progressing more or less as planned

2022: "The nuclear power station being built at Hinkley Point will start operating a year later than planned and will cost an extra £3bn, EDF has said"[0]

2021: "British Hinkley Point Nuclear Plant Delayed With Higher Costs First reactor will start producing power in June 2026. Cost will be 500 million pounds more than previously planned"[1]

2019: "Costs Rise Again for U.K. Hinkley Point Nuclear Project. Utility increases bill for Hinkley units, flags possible delay. EDF also cuts estimated return from plant to as little as 7.6%"[2]

My issue with it is more the spectacularly bad deal for the consumer that it represents. Originally the UK government insisted that "the private sector would shoulder both the development costs and risk", but then the financial crisis happened, and they ended up having to rework the deal to the benefit of EDF, who basically had them over a barrel.[3]

[0] https://www.bbc.com/news/uk-england-somerset-61519609 [1] https://www.bloomberg.com/news/articles/2021-01-27/edf-sees-... [2] https://www.bloomberg.com/news/articles/2019-09-25/edf-raise... [3] https://www.theguardian.com/news/2017/dec/21/hinkley-point-c...