by nix23 on Tuesday July 05, 2022 @06:19PM
(#31994464)
And there is also the true story when "someone" forgot to fill the tank after 5 years of regular monthly tests, then the real thing happened.
> had an electric start wired to the mains supply.
But that's a good one, humans being humans...but it worked every time before today ;))
Load and simulated power failure tests all passed.
Then some time later there was a total power cut and that's when they realised the generator had an electric start wired to the mains supply.