Re:Why are nuclear power construction costs so high? by masklinn on Thursday June 09, 2022 @03:11PM (#31685485)
TBF Flamanville 3 was a shitshow from top to bottom, starting from anyone actually taking Areva's completely unrealistic timeframes seriously: the claim was something like 3 years for the build, EDF assumed production within 4.5 years.

For a novel build of a barely finished design.

4.5 years is probably the shortest time it took to build a CP (900MW) reactor at the height of France's reactor-building frenzy (St-Laurent-B-1 construction started in May 1976 and ended in January 1981, 4 years and 8 months).

The next generation (P4) I don't think any took less than 6 years to build, and the embattled N4 generation immediately preceding the EPR the first reactor (Chooz 1, of only 4) had a build time of 12 years (and 7 months), the last (and fastest), Civaux 2, being completed in a "mere" 8 ( and 8 months).

And the N4 had and still has significant teething issues: soon after they were put into production they suffered from leaks in cooling pipes leading to all 4 being stopped for 10 months, and at the 10 years revision in 2021 extensive stress corrosion cracking of the primary circuit was discovered, all the N4s have been stopped and the last news are they won't be restarted until 2023.