Re:Nuclear fusion has encountered a shortage of tritium
by ncmncm on Sunday May 22, 2022 @02:01PM
(#31470963)
It is scheduled to be done in 2035, which means in practice for projects like this 2040 or 2045, and at $25B meaning $30B+. It will surely be abandoned before then, and we still won't know.
What were these small changes that fixed it? Did they have anything to do with the cost going up by 3x?
Anyway, inducing radioactivity is not what would use it up. That just makes it super-expensive to do repairs. It would get used up through neutron bombardment weakening the crystal structure of the metals it is constructed of.
Re:Nuclear fusion has encountered a shortage of tritium
by pfdietz on Wednesday May 25, 2022 @05:54AM
(#31502372)
No, it wasn't. ITER uses materials (like CuCrZr) that are unsuitable for a production reactor, ITER will not perform tritium breeding (except in a few experimental modules that won't be sufficient to prove that technology), and ITER will only operate at full power on DT for at most a few weeks total over its lifespan.
That was one of the main questions the ITER was supposed to answer, wasn't it? AFAIK earlier designs were quite short-lived, but some small changes fixed it. We will know how long they last as soon as we don't have an ITER anymore.