Re:Finland starts much-delayed nuclear plant, brings respite... by natmaka on Sunday March 13, 2022 @10:29AM (#30661496)
In France the 'nuclear success story' led to a state law (2015-992, from 2015, the "loi relative à la transition énergétique pour la croissance verte") stating that the part of nuke-produced electricity must fall to less than 50% in 2025, from 72% then, and that renewable sources must replace it.

In France nuke-power is backed by gas (which produced 7.5% of the gridpower in 2020).

The sole reactor currently planned (Flamanville-3) is a complete disaster, more than 12 years behind schedule, it will cost at least 19.4 billion € (initial budget: 3.7 billion €).