Time has its own cost, especially multi-stage construction projects.

Being delayed imposes costs on downstream work, which must now be ready but in some kind of holding pattern, which imposes costs on work downstream of that work.

So a large part of throwing "Manhattan project" / excess funding (and the potential savings by just funding it that way from the start) is avoiding these delays, to the extent possible.

It costs +$200,000 to tackle some challenge in a critical piece? Sometimes it's cheaper just to pay.