Why do I phrase it this way? Because the only market mechanism is a sale, you either buy or you don't. Low price is visible before a sale, so a new sale is reward for the low price offered. Quality and timeliness are only apparent after a sale, so can only be punished retroactively by not buying again.
The punishment signal is also far weaker than the reward signal, lots of goods are not bought too often and problems get forgotten by customers, alternatives may have their own problems, etc. And prices can be compared objectively for standardized goods, and at least easily for other goods. Quality and timeliness are often in the eye of the beholder, subject to variation. Comparisons in those areas are also systematically prevented by most vendors.
That's not always true. When a rail network gets privatized, the argument is that the market will make sure it's a good service still. But they are usually paid by the government, not the patrons. The commuters vote becomes negligible, and the rail network has every incentive to optimize for a minimum viable network that meets their government set targets while the service gets worse and worse in all other metrics. Seats are shittier, service is less clean, graffiti stacks up, railstock gets rickety etc.
Mid and long term cost actually turned out a lot higher than if they had chosen the better slightly more expensive bids.
Some Italian construction company underbid, and slightly later went bankrupt after finishing some of the work. They just about missed the contract milestones for payment too, and got nothing out of it. Then, the contract went to someone else who bid, with expected costs adjusted. Think there was an 8-ish month delay.
1. Submit a low bid for EXACTLY what's written in the RFP
2. Submit contract delay notifications with contract amendment offers, explaining that the original bid was incorrect and therefore if the amendment is not accepted the project can't continue.
3. rinse and repeat
No. 2 is basically legal speak to make sure you get paid(or win a lawsuit in the event that you don't) even though you can't continue construction.
It's basically saying, you made a mistake in your original RFP, therefore nobody could have continued the construction anyway and therefore you have to accept my amendment.
Good bidders will actually tell you that your RFP was wrong. As an example in the construction project I was in the main architect requested custom spliced decades outdated Fiber wiring, when I finally got a hold of the wiring company and asked them why didn't just do MTP, they mentioned that a) they mentioned to the architect that the request wiring makes no sense and b) they were not allowed to talk to us(the engineering department) directly. Same happened with the fire protection rules from anything like stair handles to the garage.
That's also why I don't think the Airport delays in Berlin were engineering mistakes but rather gross mismanagement.
Also, while in this whole project there is a lot of physical work that you can't optimize away, a lot of the physical work delays and do-overs were also due to gross mismanagement, which is something the toplevel comment completely ignores in his assessment of the 4 day workweek.
But yes any description of economics is necessarily a simplification. For example market segments where people intentionally pay more for the exclusivity that comes with being charged more.
Construction isn't like that. Companies aren't cranking out a million buildings a day, so they can't remove every ounce of unnecessary materials; they don't control the environment, making delays a fact of life; they don't control all of the companies and people involved; etc. There's just so much unknown when it comes to construction. Like software, it can be difficult to figure out how much padding to put into estimates. It's a good bit easier when it comes to things like roads, but companies still need to contend with unexpected delays a lot.