Depends on the cable. In some cases, the fiber bundle will be fully terminated at the landing, which serves as a junction point where the logical path for the cable system then resumes via a different cable to the next landing in the path. In other cases, a fraction of the fiber bundle will be split (either physically or with a subsea multiplexer device) and directed to a nearby landing, with the remainder of the fiber continuing onwards.
[ Parent
| on HN ]
Re:Google to build new undersea cable to connect Latin Ameri...
by virtuallynathan on Friday June 11, 2021 @10:45AM
(#27474086)
On these newer cables they tend to use wavelength-selective switches at BUs.