> Devs, is your team using story points to estimate work? Why/Why not?
No, but we’re using story points to consume time while still estimating work on hours. Why? Irrational mix of cargo cult practices imposed by management with no articulable rationale.
> Been going back and forth internally to understand the true value of story points in estimating sprints.
Used properly, story points mitigate various problems with estimating intellectual work; basically, teams are empirically better and chunky relative estimates than detailed time-based estimates, but also tend to waste a lot of effort for no return when doing the latter. So, ideally, with SPs you do chunky relative estimates quickly, and over time use statistical analysis tonget a picture of both the expected time and variance (both of which will slowly change over time) that those chunky relative estimates translate into for work items and overall sprint size.
A sibling comment recommends no-estimate flow based development methods, which are often ideal if the dev team has no outside interactions for which estimates matter (or these are rare and unpredictable, so that ad hoc estimation of particular items on demand is more appropriate); if you have such interactions regularly, though, you need the minimum cost way to get estimates accurate to within the limits of available information, and story points, used properly, can be part of a process that provides about the best solution to that available.
As the first part of my comment indicates, story points can be (and often are, IME) used improperly in ways which arr pure waste, too, though.
No, but we’re using story points to consume time while still estimating work on hours. Why? Irrational mix of cargo cult practices imposed by management with no articulable rationale.
> Been going back and forth internally to understand the true value of story points in estimating sprints.
Used properly, story points mitigate various problems with estimating intellectual work; basically, teams are empirically better and chunky relative estimates than detailed time-based estimates, but also tend to waste a lot of effort for no return when doing the latter. So, ideally, with SPs you do chunky relative estimates quickly, and over time use statistical analysis tonget a picture of both the expected time and variance (both of which will slowly change over time) that those chunky relative estimates translate into for work items and overall sprint size.
A sibling comment recommends no-estimate flow based development methods, which are often ideal if the dev team has no outside interactions for which estimates matter (or these are rare and unpredictable, so that ad hoc estimation of particular items on demand is more appropriate); if you have such interactions regularly, though, you need the minimum cost way to get estimates accurate to within the limits of available information, and story points, used properly, can be part of a process that provides about the best solution to that available.
As the first part of my comment indicates, story points can be (and often are, IME) used improperly in ways which arr pure waste, too, though.