Re:Why software projects take longer than you think: a stati...
by crispyambulance on Wednesday March 10, 2021 @07:50AM
(#26410700)
> I think I can work out a 95 % estimation I am willing to stake money on even without the things you mention.
I doubt it. It's dicey to do estimations even when everything is well understood, but if you lack detailed and accurate records of past work for very similar projects... the best you can do is pad like crazy, cross your fingers, meet the deadline and say your confidence interval calculation was "accurate."
Re:Why software projects take longer than you think: a stati...
by jbay808 on Friday March 12, 2021 @03:09PM
(#26440306)
If the lognormal distribution is correct, the 95% confidence interval is a bit over 5 times the developer's gut-feeling estimate. The 99% confidence interval is 10 times the developer's gut-feel estimate. We found a lot of data to back this up, but your mileage may vary.
> What I am saying is that it's better to make a good effort at estimation
But what does that estimation mean? If we don't know after the fact whether the estimation was good or bad, then it's useless because it's an answer to an unknown question, and every stakeholder will interpret it differently. In order to know after the fact, we must know ahead of time whether we're aiming for 50 %, 90 %, or something else.