Re:Samsung Foundry: New $17B Fab in the USA by Late 2023 by totalZero on Wednesday February 10, 2021 @09:43PM (#26097649)
> They kinda build the cleanrooms around ASML's machines instead of bringing them in afterwards.

I know they're massive, but do you have a source for this? I was under the impression that construction and tool installation are two distinctly separate phases of construction due to the requirements for an immaculate environment. Also, my understanding is that companies like to bring the tools in as late as possible to shorten the delay between capex outlay (tools are expensive) and first production.

Re:Samsung Foundry: New $17B Fab in the USA by Late 2023 by kokx on Thursday February 11, 2021 @08:51AM (#26101475)
My source for this is my professors at the TU/e in Eindhoven and guest lecturers from ASML (TU/e is the closest university to the ASML campus in Veldhoven).

Unfortunately I don't have a more reliable source on that though.