Intel does not run at Korean speed.
Samsung's Pyeongtaek Line 3 fab broke ground in 09/2020, construction expected to be complete by 2H/2021, mass production by 2023. This is not an unreasonable speed for Samsung.
Of course, the slower rate of work by American construction companies could slow this down.
Intel's last fab build took 9 years to go from green field to producing wafers (note...faster is possible)
https://www.tomshardware.com/news/intels-long-awaited-fab-42...
Some more realistic notes because I sound a little hyperbolic:
2011 - break ground
2013 - finish basic construction
2014 - stop progress
2017 - start install of tooling
2020 - production