Re:Software effort estimation is mostly fake research by csours on Monday January 18, 2021 @02:47PM (#25825772)
> "complete" means every single item the customer wants to see in the product,

Ah, but the customer does not know everything they want, due to the fractal nature of reality. The closer you get to the end product, the more detail is resolved, and more work is added.

Re:Software effort estimation is mostly fake research by jakubp on Monday January 18, 2021 @02:54PM (#25825850)
Oh man, thank you for the fractal nature of reality. That is the perfect term to describe what I saw about ever-changing requirements. No matter how closely you define something, things will always keep changing on all levels when closer to actually "delivering" / launching. Adding time, costs, confusion, frustration. Fractal, yes, that's it :)
Re:Software effort estimation is mostly fake research by KineticLensman on Monday January 18, 2021 @03:48PM (#25826456)
> No matter how closely you define something, things will always keep changing on all levels when closer to actually "delivering" / launching

Xeno's paradox [0] doesn't apply here. Some projects do actually finish.

[0] https://en.wikipedia.org/wiki/Zeno%27s_paradoxes#Achilles_an...

Re:Software effort estimation is mostly fake research by KineticLensman on Monday January 18, 2021 @03:45PM (#25826421)
Another way of looking at this is that (unless there is a complete disaster) as you get closer to the end the uncertainty in the estimate decreases. When you get to the end, you know precisely how long it took.
Re:Software effort estimation is mostly fake research by cmroanirgo on Monday January 18, 2021 @02:57PM (#25825882)
Although this sounds flippant, the design process is where unknowns should be uncovered. It is easier to change design before a line of code is written. Design is precisely what is needed in order for the dev team to break down the projects into tiny chunks where nothing is unknown.

Your time estimates should always include time for research and design. The customer can sign off on what you're about to write at the end of that (whereas beforehand you give them a wild ballpark figure made by senior devs - not management!)

Re:Software effort estimation is mostly fake research by ubercore on Monday January 18, 2021 @03:23PM (#25826168)
Yeah but too many customers change their mind even after they've signed off. Then you're left with strictly enforcing a contract or making adaptations.

You're right, design is very very necessary and should be given plenty of time. But it's not a magic bullet.

Re:Software effort estimation is mostly fake research by 1337shadow on Monday January 18, 2021 @03:53PM (#25826507)
In terms of contract, I have found this works best (recommended by my lawyer (a former ASF lawyer)): 30% upfront, 50% at first delivery, then they have 2 months to find bugs, final delivery is when the bugs are fixed that's when you take the last 20%. This way, you're certain to always get 80%.

If they want the liberty to "change their mind on the fly" then they should buy man-days which is a completely other thing. Or, they can buy supplementary mandays for whatever they want at the daily rate without changing the contract, or, they can just wait to finish this contract and start another one.

Re:Software effort estimation is mostly fake research by chasd00 on Monday January 18, 2021 @05:23PM (#25827419)
it's pretty a well known saying that the last 10% of any project takes 90% of the time.