by M2Ys4U on Thursday August 20, 2020 @07:06AM
(#24221990)
The Metrolink in Manchester,[0] the UK's largest tram network, is a good counter-example.
The expansion of the network been consistently well delivered over the last ~decade.
The Airport Line opened a year ahead of schedule,[1] the Trafford Park line eight months ahead of schedule,[2] and the Second City Crossing was only a year behind it's aspirational opening date because of the discovery of a crypt buried under where a new station was being built.[3]
I think this is mainly because there has been a pipeline of new projects enabling both the contractors and TfGM to retain skilled engineering and project management staff.
The expansion of the network been consistently well delivered over the last ~decade.
The Airport Line opened a year ahead of schedule,[1] the Trafford Park line eight months ahead of schedule,[2] and the Second City Crossing was only a year behind it's aspirational opening date because of the discovery of a crypt buried under where a new station was being built.[3]
I think this is mainly because there has been a pipeline of new projects enabling both the contractors and TfGM to retain skilled engineering and project management staff.
[0] https://en.wikipedia.org/wiki/Manchester_Metrolink
[1] https://www.bbc.co.uk/news/uk-england-manchester-29879147
[2] https://www.bbc.co.uk/news/uk-england-manchester-51801265
[3] https://www.bbc.co.uk/news/uk-england-manchester-30779807