Disable the turbine. Kill AC power (turn off all the rectifiers and HVAC) and let the office run on battery for a while. Closely monitor the batteries, and the temperature in critical areas.
After a good while on battery (an hour or two, if I recall), walk leisurely over to the turbine and enable it. Let it start and warm up, then transfer the rectifiers and HVAC over to generator power.
Closely monitor the turbine while the batteries recharge, the HVAC while on unusual power, and the humans who are really glad to have air conditioning back.
When satisfied that all is copacetic, transfer things back to utility AC, shut down the turbine, and call the fuel company to top off the tank.
Most of the batteries in these offices were between 10 and 20 years old, with a couple instances of the beautiful cylindrical "Bell Cells" still in service. They were sized to not break a sweat running the whole building, and impeccably maintained, so they didn't tend to fail prematurely.
Once a quarter we'd do a live load transfer, and watch all the PDUs and UPS systems do their thing. Those could be stressful...
http://resistive-loadbank.sell.everychina.com/p-109417602-35... is the first example I pulled up, and there are bigger ones.
I don't have actual knowledge of nuclear power plants, that is classified beyond the public. However hospitals do the above, because if thing dont work on a bright sunny day how do you think they will work when a tornado has not only taken out power, but also filled the er with server trauma cases.
The cardinal rule is - test everything. Test it when you install and commission it, test it when part of the system changes, test it periodically during maintenance shutdowns, test it when you have a convenient time to do so without losing production (such as an outage to a different system that necessitates your system being offline).
Test components individually - at the factory and in the field - and test systems end-to-end.
Test with the most adverse possible conditions, not the most optimal. Test beyond your normal operating envelope.
When I participate in design reviews as a maintenance engineer my primary line of inquiry is: how will I test this stuff during operations? Has it been designed in a way that makes testing impossible without an expensive outage? Can workers safely gain access to components that need routine testing without having to de-energize other, unrelated parts of the system?
Now not every industry has the budget available to test to the extent that we do. But even in our industry, I often see a penny-wise, pound-foolish approach of "assume this thing works perfectly from the factory then act surprised years later when an abnormal condition occurs and it fails".
If something was not tested, it may not work. It might be for a very simple reason (like mis-configuration of a single setting during installation) or a very complex reason. But either way, wouldn't the company rather know their equipment doesn't work -before- putting it into service than after?