Re:Mythical man month: 10 lines per developer day
by HillRat on Wednesday February 12, 2020 @09:44AM
(#22309159)
Fundamentally, that’s why SLOC can be useful as an estimating metric, but terrible as a control metric. SLOC, FP and so on all have their limitations, but they demonstrate that most of the effort-time in a project doesn’t go into putting hands on keyboard. Conversely, trying to monitor developer productivity with SLOC simply reintroduces the conceptual error that the estimation effort attempts to prevent.
[ Parent
| on HN ]
Re:Mythical man month: 10 lines per developer day
by skore on Wednesday February 12, 2020 @11:53AM
(#22310402)
Goodhart's law - "When a measure becomes a target, it ceases to be a good measure."
I used to work for a company that bills their customers for dev hours spent. The software they put together worked fabulously well - in the production of billable dev hours.