I don't get why you think comparing to offshore wind is misleading, though. Could you expand on that?
Wind: "The costs for a utility scale wind turbine range from about $1.3 million to $2.2 million per MW of nameplate capacity installed." http://www.windustry.org/how_much_do_wind_turbines_cost
Nuclear: " Companies that are planning new nuclear units are currently indicating that the total costs (including escalation and financing costs) will be in the range of $5,500/kW to $8,100/kW or between $6 billion and $9 billion for each 1,100 MW plant." https://www.synapse-energy.com/sites/default/files/SynapsePa...
If we look at the costs of constructing new nuclear plants (which the article we comment on is about), France is a particularly bad example, with current costs already at $11B for 1600MW of capacity for the Flamanville project. https://www.reuters.com/article/us-edf-nuclear-flamanville/e...
https://bilan-electrique-2018.rte-france.com/eolien/
Also there is currently no offshore wind park, as only offshore would approach the 50% capacity factor, but they won't, they will be in the 43% as estimated by renewables.ninja
The price of the MWh of offsore park will be from 44 to 150€/MWh, where EDF is forced to sell its nuclear at 42€/MWh, average price of wind in 2020 93€/MWh.