The electricity provider normally sells the charger with installation for ~2500E. But that is assuming the end-to-end wiring already supports this. With dozens of chargers to install in the same parking the chances that the rest of the network was already so overspeced and up to the task are slim.
The manpower to dig a trench, replace cables and transformers is more or less the same whether you do do it for 10 parking spots or 100. So there's probably a sweet spot between having enough demand to split this between more people but not that much that you need the next level in transformers.
I live in Finland, where it is typical that blocks of flats as well as terraced and single-family houses have parking lots where there already is an electric supply to each car (for the purpose of heating the enging before winter morning starts). Even here it's not directly suitable for charging, because the feeding capacity is OK for warming cars, but not for quick charging. Fuse boxes and feeding cables have to be replaced, at a substantial cost.
Some people are afraid of adverse health effects of power lines (claiming cancer issues etc, which are fake news), but often it may also be just that powerlines are considered ugly, and seeing them from your window brings down your property value.
Later edit. Ok, that makes sense. For some reason I read it as "upgrading the residential grid to support the extra load of EV charging". There are already HV power distribution lines spanning the country. I understand building new transmission towers would be a NIMBY topic but is it a given that they can't be upgraded to expand the capacity over the same towers?
Likewise for Sweden: there is hydro and other capacity in north, but power grid cannot transfer enough power to users in Skåne (Malmö) so that industrial projects are cancelled.
What would be the reason for people to oppose developing the grid, especially as NIMBY? Other than the obvious cost issue, is it the disruption caused by works?