Re:AgileFall – When Waterfall Sneaks Back into Agile by markrages on Wednesday September 18, 2019 @09:22AM (#21005108)
Agile works OK for electronics. I have done it.

With quick-turn fab houses, you can do two-week sprints in hardware. You can fix up the circuit with X-acto/bluewire changes, and roll the fixes into the next sprint. Or you can make individual subsystems per sprint.

And with firmware, most software methodologies work with minor changes.

Usually you can get something working in the first sprint, and iterate from there.

Re:AgileFall – When Waterfall Sneaks Back into Agile by roland35 on Wednesday September 18, 2019 @09:37AM (#21005259)
Your absolutely right, and with a modular system design it can make it easier to plug in iterations of individual components. But at some point early in the design you need to lay out how the modules will work together, i.e. do we use CAN? 24V power or 48V? All that can be changed as well but at some point it gets complicated!

For a simple project all of that can be managed iteratively.

Re:AgileFall – When Waterfall Sneaks Back into Agile by InternetOfStuff on Wednesday September 18, 2019 @10:34AM (#21005834)
> All that can be changed as well but at some point it gets complicated!

Not everything has to be changed, that's just a strawman.

But not every detail has to be nailed down at the beginning either.

The idea behind Agile is to reduce risk. If there is no risk of the bus system changing on you, there's no harm in fixing it right at the beginning.

But if there is a chance it might, you'd do well to have systems in place which enable you to react to changes with a minimum (though non-zero, of course) amount of pain.

Re:AgileFall – When Waterfall Sneaks Back into Agile by organsnyder on Wednesday September 18, 2019 @02:56PM (#21008711)
All the more reason to use an agile approach! The only reason you would be making those major changes is in the face of new information: a change in requirements, an unforeseen challenge, etc.

It's impossible to foresee those all in advance—better to adopt a system that is structured to anticipate them. "Unknown unknowns" are a fact of life, no matter how disciplined we believe we are with our preparation.

Re:AgileFall – When Waterfall Sneaks Back into Agile by aidenn0 on Wednesday September 18, 2019 @02:22PM (#21008360)
The same is true with software, unless you suggest that Agile will change the implementation language with every sprint...
Re:AgileFall – When Waterfall Sneaks Back into Agile by Angostura on Wednesday September 18, 2019 @10:01AM (#21005506)
Sounds like it could lead to bit if a tech support nightmare though?

"Ah, you have hardware version 2.3.1.3 - yes, it does sometimes emit sparks - we fixed that in the version that came out the month after."

Re:AgileFall – When Waterfall Sneaks Back into Agile by BurningFrog on Wednesday September 18, 2019 @11:38AM (#21006493)
You can have many internal iterations and release new versions to production very rarely.
Re:AgileFall – When Waterfall Sneaks Back into Agile by GhettoMaestro on Wednesday September 18, 2019 @10:56AM (#21006068)
Something that emits sparks should not be in the field. It should be recalled/replaced with a safe piece of hardware.
Re:AgileFall – When Waterfall Sneaks Back into Agile by Angostura on Wednesday September 18, 2019 @11:39AM (#21006505)
Feel free to amend 'emits sparks' to read 'has hardware bug X'.
Re:AgileFall – When Waterfall Sneaks Back into Agile by GhettoMaestro on Wednesday September 18, 2019 @11:57AM (#21006689)
Wrong. There are hardware bugs that do not manifest as physical safety risks.

Physical safety risks are an exceptional class of defects that in most jurisdictions has a legal requirement for the vendor to fix or replace the defective part(s) at their own cost (not to be borne by consumer).

Point: SPECTRE/MELTDOWN were not "physical safety risks". Yes you can argue they are security risks, but they didn't physically manifest as a physical safety risk which can lead to severe injury or loss of life.

Re:AgileFall – When Waterfall Sneaks Back into Agile by Angostura on Wednesday September 18, 2019 @07:21PM (#21011557)
I'm not sure what point you are trying to make. I said amend it to make it a hardware fault of your choice, or make those sparks a bit of static.
Re:AgileFall – When Waterfall Sneaks Back into Agile by GhettoMaestro on Thursday September 19, 2019 @12:15PM (#21017652)
My point was that a physical safety risk is a special kind of "hardware bug". It is not just another hardware bug, of a different flavor.

Your commentary seemed to suggest you were not attaching an appropriate level of mental priority with regards to the severity and risk.