http://www.pgecurrents.com/2017/10/31/facts-about-undergroun...
This is part of the trillion dollar sprawl problem we have. We have built a massive amount of infrastructure as cheap as possible, and now we cant afford to built it correctly. People would have never built houses in many places if they had to pay the actual costs.
Something I was reading recently claimed that total operational costs on underground lines also higher in the long run - dielectrics break down, faults are much more expensive etc. Found it counterintuitive, but hard to counter.
The article further talks about people outraged by the amount spent on digging down these cables, as they are generally high voltage cables, and not those that actually reach houses. So I'd imagine regular wires cost less than the above calculation (which includes the 5.7 billion for purchasing the original wires).
[0] In Danish: https://ing.dk/artikel/nyt-opror-stop-milliard-fras-pa-grave...
Edit: A commenter further down noted:
> PG&E has 81,000 miles of distribution lines
So that's 130,357 kilometers. So at the same cost per km as Denmark, 5,312,500 DKK /km, that's 692,521,562,500 DKK or $105,117,847,971.88 USD, ($105.12 billion) USD.
Not considering how many miles of that is actually through mountain ranges and the extra cost of doing highly remote work.
That being said, I do get an impression that more money is lost in bureaucracy/company "fees" in the US than in Denmark.
https://www.elp.com/articles/powergrid_international/print/v...