Very cool process but this seems antithetical to the tech world which is often driven by agile processes, right? I can’t imagine a business leader being happy about making decisions that should be “agile” on dated information. This seems a bit like lying to get away with working on pet projects unhindered by product/business. Am I way off-base and misunderstanding the suggestion here?
[ Parent
| on HN ]
It works with agile. You just have to sandbag a bit. Doesn't have to be 3months in an agile organization, just work for a sprint, then tell manager that's your plan for next sprint. If they change plan, you'll naturally have a 1 sprint slip, and in Sprint 2 you plan the previous sprint's worth. Or do this on the week or day level.