Re:The True Cost of Rewrites
by groestl on Saturday December 15, 2018 @11:56AM
(#18689132)
That's why a good strategy is to never put yourself in the position to communicate a timeline. If you are knowledgeable enough about a project so you can make an informed decision that a rewrite is required, the strangler pattern can allow you to complete such a project without ever formally requesting a "rewrite".
[ Parent
| on HN ]
If the executives don't get a timeline from you, they'll get it from someone less knowledgeable. Estimates made in ignorance are almost always underestimates because they omit critical work the estimator is unaware of. Therefore, this (bad) estimate will also be a "lowball" estimate, but it will be the only hard number executives have to make their decision. So they'll greenlight the rewrite and more than likely put the lowball estimator in charge. Being vocal, honest, and credible about estimates and the true cost of projects is always the best move.