Re:Why Development Teams Struggle to Deliver on Time, on Bud... by wvenable on Tuesday June 05, 2018 @01:02PM (#17239665)
Estimates in software are effectively experienced guesses. This is in contrast to other industries, such as construction, where planning is done for months to ensure the estimate of time and materials is accurate. If you attempt to treat one as the other, you run into huge problems.

Software isn't like building a bridge; it's like planning to build the bridge.

I'm pretty good at software estimating; I can roughly tell when something will take an hour, 2 hours, 4 hours, a day, a week, or month, 3 months, or 6 months -- in those intervals. It's more difficult and time consuming to get more specific than that.

I've also had a 1 day task blow out to entire week more than a few times. At that point, you have to start questioning the predictive value of estimates.

Re:Why Development Teams Struggle to Deliver on Time, on Bud... by ghettoimp on Tuesday June 05, 2018 @04:39PM (#17241819)
Heh. But even in construction projects, serious cost/time overruns are very common. I can't find a good source through quick googling, but what I do find is horrifying.
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by jacques_chester on Tuesday June 05, 2018 @09:00PM (#17243568)
Industrial Megaprojects by Edward W. Merrow essentially shows that we're comparing ourselves to a myth of our own invention.
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by ghettoimp on Tuesday June 05, 2018 @09:52PM (#17243799)
Thanks, wow, this looks like a really interesting read!
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by jacques_chester on Wednesday June 06, 2018 @01:36AM (#17244578)
It is actually quite fascinating to see how our cousins get on. He's quite blunt about the dynamics that cause failure and that relatively few megaprojects ever live up to their business case.